Guide

Flushing and cleaning a TCS loop before commissioning

A technology cooling loop is only as clean as its commissioning. This guide summarises the Open Compute Project's pre-commissioning guidance for TCS row manifolds and shows where flanges come into it.

Updated 18 October 2026 · Rajendra Industrial Corporation

A TCS loop is hydro tested at 1.3 to 1.5 times working pressure, recirculated and cleaned until clear, flushed at 3 to 5 ft/s until conductivity is close to the procedure water value, filtered down to about 5 microns, then filled with coolant or dried and blanketed with nitrogen.

Before you start

Cleaning cannot fix the wrong material. Confirm that pipe, fittings, flanges and valves are stainless or another approved wetted material, that stainless items arrived treated to ASTM A380, and that welds were made with an inert gas purge. Positive material identification on incoming flanges and fittings catches mix-ups before they are welded in.

Step by step

TCS pre-commissioning sequence, summarised from the OCP guidance
StageWhat happensTargets
Hydrostatic testFill slowly from a low point, vent at high points, hold test pressure1.3 to 1.5 times working pressure; do not break joints that passed
Initial recirculationCirculate through temporary filters until clearTurbidity under 20 NTU; at least 3 system volumes
CleaningCirculate a caustic cleanerAt least 4 hours; no rise in filter pressure drop for 1 hour
FlushingDrain and refill with procedure water, recirculateAt least 8 system volumes per cycle; 3 to 5 ft/s
End pointRepeat flushing until cleanConductivity within 10 to 20 µS/cm of procedure water, or 60 µS/cm max; turbidity under 5 NTU
Lay-up or fillFill with glycol coolant, or drain, dry and blanketDry nitrogen blanket; compressed air only to ISO 8573-1 Class 2
Procedure water and filtration
ParameterValue
Procedure water conductivity50 µS/cm max
Procedure water pH6 min
Total aerobic bacteria1,000 CFU/ml max
First stage filtration50 to 100 µm
Final filtration5 µm recommended (1 to 25 µm industry range)
Filter changeAt about 10 psi pressure drop
Do not let it sit

Flush immediately after cleaning, and do not leave water stagnant in the loop for more than 24 hours without chemical treatment. Bacteria grow quickly in warm, untreated water.

Where flanges help

  • Flushing connections: 316L blind flanges on header ends become connection points for temporary pumps and filter skids.
  • Bypasses: flanged spools let installers take cold plates, manifolds and heat exchangers out of the cleaning circuit and replace them with jumpers.
  • Crevice-free joints: weld neck and stub end joints flush out more easily than slip-ons with internal fillet welds.

Frequently asked questions

Should the cold plates be in the loop during flushing?

Keep equipment with fine passages, such as cold plates, rack manifolds and plate heat exchangers, out of the initial cleaning and flushing circuit, using bypasses or jumpers, so debris is not driven into them. Follow the equipment and coolant suppliers' procedures.

How fine should the final filtration be?

The OCP guide recommends 5 microns final filtration, noting an industry range of 1 to 25 microns, with a first stage of 50 to 100 microns.

Can the flushed loop be left full of water?

Not for long. The guide warns against leaving water stagnant for more than 24 hours without chemical treatment. Fill with coolant promptly, or drain, dry and blanket the loop with dry nitrogen.

Source

Open Compute Project, guidelines for pre-commission preparation of technology cooling system (TCS) row manifolds in liquid-cooled data centers. Always follow the version adopted by your project and the coolant supplier's instructions.

Request for quotation

Send us your flange schedule

A line list, a BOM or a marked-up drawing all work. For each line item, tell us:

  • Flange type, face and size (NPS or DN)
  • Standard and pressure class, for example ASME B16.5 Class 150 or EN 1092-1 PN16
  • Material grade and the loop it goes on, for example 316L on the TCS loop
  • Quantity, inspection requirements and destination